Short answer

Curtain walling in the UK is covered by the product standard BS EN 13830, which sets performance characteristics such as air permeability, watertightness and wind resistance. In England, Regulation 7(2) restricts materials in external walls of relevant buildings at least 18 metres high. Higher-risk buildings go through the Building Safety Regulator under the Building Safety Act 2022. CDM 2015 and the Work at Height Regulations 2005 apply to installation and maintenance.

Curtain Walling Regulations UK: Standards, Fire and Building Safety

BS EN 13830: the product standard

BS EN 13830 is the product standard for curtain walling. It sets out the performance characteristics that need to be declared, including air permeability, watertightness, resistance to wind load, impact resistance, thermal transmittance and acoustic performance, along with the test methods used. Manufacturers and system suppliers use it to describe how their systems perform.

On projects, specifiers use these characteristics to set the required performance for the facade, based on building height, exposure and use. Many specifications also refer to industry guidance and testing protocols, and require test evidence for the system and sometimes for a project-specific sample. Ask suppliers for declared performance and test evidence when comparing systems.

Fire safety and Regulation 7(2)

In England, Regulation 7(2) of the Building Regulations 2010 restricts the materials that can become part of the external wall of a relevant building. Relevant buildings are broadly those at least 18 metres high containing a dwelling, along with certain other uses such as residential care homes, hospitals and student accommodation. Materials generally need to achieve Class A2-s1, d0 or A1 under the relevant classification.

There are listed exemptions for certain components, such as window frames, glass, seals, gaskets and some other items, which matters for curtain walling where framing, glass and gaskets are core parts of the system. Spandrel panels, insulation and other materials within the external wall still need to comply. Approved Document B also covers cavity barriers and fire-stopping, including at slab edges behind curtain walling.

RuleWhat it coversWho it affects
BS EN 13830Curtain walling performance characteristicsManufacturers, specifiers
Regulation 7(2)Restricted external wall materialsRelevant buildings 18m+, England
Approved Document BFire spread, cavity barriers, fire-stoppingAll buildings
Building Safety Act 2022Higher-risk building regimeResidential 18m+ or 7+ storeys
CDM 2015Health and safety managementAll construction work
Work at Height Regulations 2005Planning and equipment for height workInstallers and maintainers

The Building Safety Act 2022

The Building Safety Act 2022 introduced a new regime for higher-risk buildings in England, broadly residential buildings at least 18 metres or seven storeys tall with at least two residential units, along with some other types. Building control for these buildings is carried out by the Building Safety Regulator rather than local authorities or registered building control approvers.

For new higher-risk buildings and major work on existing ones, approval is needed at set gateway stages before construction starts and before occupation. Detailed design information about the external wall, including curtain walling, fire performance and how it has been tested or assessed, must be provided. Changes during construction are controlled. This affects design timelines and the documentation curtain walling contractors must produce.

  • Confirm early whether the building is higher-risk
  • Allow time for regulator approval before work starts
  • Keep full records of products, tests and installation
  • Control and record any design changes during construction
  • Make sure fire-stopping and cavity barriers are inspected and recorded

Health and safety during installation

The Construction (Design and Management) Regulations 2015 apply to curtain walling projects, including repairs and maintenance. Clients, designers and contractors have duties to plan, manage and monitor work to control risks. On larger projects, a principal designer and principal contractor must be appointed, and a construction phase plan prepared.

Curtain walling work involves significant work at height, heavy lifting of glass and panels and interfaces with other trades. The Work at Height Regulations 2005 require this work to be properly planned, supervised and carried out with suitable equipment. Safe systems for lifting glass, edge protection, exclusion zones and competent operatives are all essential.

Thermal and energy requirements

Curtain walling forms part of the thermal envelope and must meet the energy efficiency requirements of Approved Document L in England. For new buildings, this feeds into the overall energy calculations. For replacement facades on existing buildings, there are limiting U-values for the new elements. The thermal performance depends on the framing, glass, spandrel panels and how well junctions are detailed.

Condensation risk is also part of good design. Thermally broken frames, warm-edge spacers and properly insulated spandrel zones reduce the risk of condensation forming inside. Thermal modelling at design stage helps confirm the facade will perform as expected and highlights weak points before fabrication begins.

Scotland and Wales

Scotland and Wales have their own building regulations and technical guidance. Scotland uses building standards and technical handbooks with its own requirements on external wall cladding and fire spread, including height thresholds that differ from England. Wales has its own regulations and has introduced its own approach to external wall materials on certain buildings.

If you are working on a project outside England, check the local requirements early and appoint designers and contractors familiar with them. The general principles are similar, protecting against fire spread, ensuring performance and keeping workers safe, but the details, thresholds and approval routes vary.

Questions people also ask

Is glass in curtain walling affected by the combustible cladding ban?

Regulation 7(2) in England includes exemptions for certain components, including glass, window frames, seals and gaskets. However, other materials in the external wall, such as spandrel panel insulation and some backing materials, must still comply. Designers should check each component carefully against the regulation and Approved Document B.

What is a higher-risk building?

Under the Building Safety Act 2022, a higher-risk building in England is broadly one at least 18 metres or seven storeys tall with at least two residential units, plus certain hospitals and care homes during construction. These buildings go through the Building Safety Regulator for building control approval.

What does BS EN 13830 cover?

BS EN 13830 is the product standard for curtain walling. It sets out the performance characteristics that must be declared, such as air permeability, watertightness, resistance to wind load and thermal transmittance, along with the methods used to test and assess them.

Written and checked by the Curtain Walling team. Read our editorial policy.

Get a free curtain walling quote

Tell us what you need and we'll come back with a clear price.

Request a quote