Stick vs Unitised Curtain Walling: Differences, Pros and Cons

Short answer

Stick curtain walling is assembled on site from mullions, transoms and glass, costing about £450–£850 per m². It suits low to mid-rise buildings, complex shapes and smaller areas. Unitised curtain walling is built and glazed as panels in a factory and lifted into place, costing about £700–£1,300 per m². It suits tall buildings, fast programmes and repetitive facades where factory quality control matters.

Stick vs Unitised Curtain Walling: Differences, Pros and Cons

How stick systems work

In a stick system, the framing is installed piece by piece on site. Vertical mullions are fixed to brackets on the slab edges or structural frame, horizontal transoms are fitted between them, and then glass units and panels are installed and sealed with gaskets and pressure plates or structural silicone. Caps are clipped over the outside to finish the look, or the system is designed with a flush glass appearance.

Stick systems are flexible. They adapt well to irregular grids, angles, curves and changes in the building's shape, and they are economical for smaller facades because there is no need for factory panel assembly and large lifting operations. The trade-off is more work on site, which means more exposure to weather and a heavier dependence on site workmanship.

How unitised systems work

Unitised curtain walling is made of large panels, often one storey high and one module wide, that are fabricated, glazed and sealed in a factory. The finished panels are delivered to site, lifted into position and hooked onto brackets at each floor. Adjacent panels interlock along their edges with gaskets, forming the weather seal.

Because most work happens in controlled factory conditions, quality is more consistent and site installation is much faster. Panels are usually installed from inside the building, which reduces the need for external scaffold. Unitised systems need longer lead times for design and fabrication, careful logistics for delivery and storage, and suitable lifting equipment, which makes them best suited to larger, taller and more repetitive facades.

Side-by-side comparison

The table summarises the main differences that usually guide the choice between the two systems.

FactorStick systemUnitised system
Typical cost£450–£850 per m²£700–£1,300 per m²
Where assembledOn siteIn a factory
Site installation speedSlowerFaster
Quality controlDepends on site workFactory controlled
External accessScaffold or mast climbersOften installed from inside
Best building heightLow to mid-riseMid to high-rise
Design lead timeShorterLonger

Choosing the right system

The decision usually comes down to height, area, programme and design complexity. On a two to four storey office, school or retail building, a stick system is often the most economical and flexible choice. On a tower where scaffold would be expensive and the facade needs to be weathertight quickly so fit-out can start, unitised panels often make more sense despite the higher rate.

Repetition matters. Unitised systems are most efficient when many panels are the same size and type, because the factory can produce them in a steady flow. Highly varied facades with many one-off panels lose some of that efficiency. Some projects use both: unitised panels for the main tower and a stick system for the podium, entrance or awkward areas.

  • Choose stick for low-rise, varied geometry and smaller areas
  • Choose unitised for height, speed and repetitive grids
  • Consider crane availability and site storage space for unitised panels
  • Allow longer design and lead time for unitised systems
  • Check how each system interfaces with other cladding and the roof
  • Plan future replacement access for glass in either system

Performance and maintenance

Both systems can achieve high levels of air tightness, watertightness, thermal performance and wind resistance when properly designed and installed. Curtain walling products in the UK are covered by BS EN 13830, which sets out the performance characteristics to be declared, such as air permeability, watertightness and resistance to wind load. Projects often also specify testing to confirm performance.

Maintenance differs slightly. In stick systems, individual glass units can usually be replaced from outside by removing caps and pressure plates. In unitised systems, glass replacement depends on the design, and some panels are glazed so units can be changed from inside, while others need external access. Ask how glass will be replaced in future before choosing a system.

Common pitfalls

Many curtain walling problems come from interfaces rather than the system itself. Junctions with the roof, ground level, slab edges and adjoining cladding need careful design and installation to stay watertight and to maintain fire separation between floors. Poor sealing at these junctions is a frequent cause of leaks in both stick and unitised facades.

With stick systems, rushed site work, poor sealing at joints and blocked drainage are common issues. With unitised systems, damaged panels from careless handling, poorly sealed stack joints and tolerance problems with the building frame can cause trouble. Experienced installers, clear interface drawings and inspection during installation all reduce these risks.

Questions to ask a curtain walling contractor

Before appointing a contractor, ask them to explain why they recommend one system over the other for your building, and what that means for cost, programme and access. Ask for examples of similar buildings they have completed with the proposed system, and how they manage design responsibility, including structural calculations, thermal modelling and interface details with the frame and other trades.

For unitised work, ask about factory capacity, delivery logistics, site storage, lifting plans and how damaged panels will be handled. For stick systems, ask about site supervision, sealing procedures at joints and how quality will be checked floor by floor. In both cases, ask what testing is included, how glass will be replaced in future, and what maintenance the system will need. Clear answers to these questions are a good sign that the contractor understands the risks and has planned for them rather than simply pricing a square metre rate.

Questions people also ask

Which is faster to install, stick or unitised curtain walling?

Unitised curtain walling is much faster on site because panels arrive pre-glazed and simply need lifting and connecting. However, design and factory fabrication take longer, so the overall timeline depends on when design can be finalised. Stick systems start on site sooner but take longer to complete.

Can stick curtain walling be used on tall buildings?

It can, but it becomes less practical as height increases because of the access, scaffolding and site labour needed. Above a certain height, unitised systems are usually preferred. On relevant buildings at least 18 metres high in England, external wall materials must also meet Regulation 7(2) restrictions.

Is unitised curtain walling better quality?

Unitised panels benefit from factory quality control, so consistency is usually very good. But a well-designed stick system installed by an experienced team can perform just as well. Quality depends on design, workmanship, interfaces and inspection, not just the system type.